| S. No. |
Name of work |
Date of starting |
Date of completion |
Cleints |
| 1. |
CTR with 75 ‘R’ Rail and dual gauge PSC sleeper from km 31/0 – 51/0 between Rangiya-Rangapara by PQRS Machine. |
28.01.2006 |
22.05.2006 |
DRM Rangiya, N.F.Railways
|
| 2. |
CTR with 75 ‘R’ Rail and dual gauge PSC sleeper from km 50/0 – 61/0 and 70/0 – 96/0 between Rangiya-Rangapara by PQRS Machine with PQRS base depot at Rowta Bagan and other ancillary works.
|
27.03.2006 |
30.10.2006 |
DRM Rangiya, N.F.Railways
|
| 3. |
45 kms Relaying by TRT between Shikohabad – Farrukhabad branch line.
|
04.04.2005 |
20.07.2006 |
DRM Allahabad, N.C Railways
|
| 4. |
Misc. work for working of TRT Machine for TSR between Delhi-Shahdara-Shamli-Saharanpur sections.
|
23.04.2003 |
30.08.2004 |
DRM New Delhi, Narthem Railways
|
| 5. |
30 km Relaying by TRT between NEW-JHS section.
|
28.07.2004 |
31.03.2005 |
DRM Jhansi, N.C Railways
|
| 6. |
A) 53 km Relaying by TRT between km 1192-1224 and 1266-1287.
B) Deep Screening & Misc. work in connection with CTR work.
|
05.05.2003 |
31.03.2005 |
DRM Jhansi, N.C.Railways
|
| 7. |
CTR 46.42 Tkms by PQRS between BRB-PPJ station.
|
23.10.2001 |
22.10.2002 |
DRM Solapur, Central Railways
|
| 8. |
TRR of BG track 72.99 km of existing 90 R rails on wooden/ST/PSC sleepers (M+7) density with 52 kg (90UTS) rail (LWR) on BKN-SOG section.
|
01.08.2005 |
15.04.2007 |
DRM Binkaner, N.W Railways
|
| 9. |
CTR 14.90 KM BY PQRS and 2.00 km manually |
11-10-07 |
15-3-2008 |
DRM pune, Central railways
|
| 10. |
CTR 16.90 KM BY PQRS and 4.00 km manually |
8-5-06 |
28-10-06 |
DRM pune, Central railwa
|
| 11. |
CTR (Primary) of 13.65 km in the section of KUN-KKDE. |
25-7-05 |
17-3-06 |
DRM NEW DELHI, Northern railways
|
| 12. |
CTR (Secondary) From Km 11.2 between PRG-PBH-SLN sections. |
5-1-06 |
12-5-06 |
DRM lucknow, Northern railways
|
| 13. |
A)9.10 Km CTR (P) Work by PQRS between Km 1193.00 to 1202.10 on DN Line of JHS-GWL section.
B) CTR (P) work by PQRS between HET-GHER section on GWL-AGC section. |
08.08.2007 |
12.3.2008 |
DRM (W) Jhansi, N.C. Railways
|
| 14. |
45 Km TSR by TRT in MTJ-AWR section. |
04.01.2006 |
13.10.2008 |
DRM (W) Agra, N.C. Railways
|
| 15. |
Linking & Dismantling of BG Track Turnouts, Provision of SEJ, Glued Joints, Spreading of ballast, Leading of P.Way material and other misc. work from Km 1028.170 to 1013.355 between Anup Ganj-Chhandrauli section and Doubling between Utratla-Chhandrauli and Sultanpur-Bandhua Kalan section. |
27.08.2007 |
24.4.2008 |
Dy. Chief Enguneer (C0nst), Kashmere Gate, Delhi, Northen Railways
|
| 16. |
CTR(S) of 10 km and TRR(S) of 2.5 km in loop line and Renewal of fan shaped turnout at various section on Delhi-Ambala section. |
08.12.2006 |
26.5.2007 |
DRM New Delhi, Northern Railways
|