Rail Tech Infraventure Pvt. Ltd.(Rail Infrastructure Company; Railway civil & track work; Depot flash-butt welding; Mobile flash-butt welding; Merry go round rail system; Mechanised track laying and linking; PQRS Work)
Completed Projects | Running Projects
 
 
S. No. Name of work Date of starting Date of completion Cleints
1. CTR with 75 ‘R’ Rail and dual gauge PSC sleeper from km 31/0 – 51/0 between Rangiya-Rangapara by PQRS Machine. 28.01.2006 22.05.2006 DRM Rangiya, N.F.Railways
2. CTR with 75 ‘R’ Rail and dual gauge PSC sleeper from km 50/0 – 61/0 and 70/0 – 96/0 between Rangiya-Rangapara by PQRS Machine with PQRS base depot at Rowta Bagan and other ancillary works. 27.03.2006 30.10.2006 DRM Rangiya, N.F.Railways
3. 45 kms Relaying by TRT between Shikohabad – Farrukhabad branch line. 04.04.2005 20.07.2006 DRM Allahabad, N.C Railways
4. Misc. work for working of TRT Machine for TSR between Delhi-Shahdara-Shamli-Saharanpur sections. 23.04.2003 30.08.2004 DRM New Delhi, Narthem Railways
5. 30 km Relaying by TRT between NEW-JHS section. 28.07.2004 31.03.2005 DRM Jhansi, N.C Railways
6. A) 53 km Relaying by TRT between km 1192-1224 and 1266-1287. B) Deep Screening & Misc. work in connection with CTR work. 05.05.2003 31.03.2005 DRM Jhansi, N.C.Railways
7. CTR 46.42 Tkms by PQRS between BRB-PPJ station. 23.10.2001 22.10.2002 DRM Solapur, Central Railways
8. TRR of BG track 72.99 km of existing 90 R rails on wooden/ST/PSC sleepers (M+7) density with 52 kg (90UTS) rail (LWR) on BKN-SOG section. 01.08.2005 15.04.2007 DRM Binkaner, N.W Railways
9. CTR 14.90 KM BY PQRS and 2.00 km manually 11-10-07 15-3-2008 DRM pune, Central railways
10. CTR 16.90 KM BY PQRS and 4.00 km manually 8-5-06 28-10-06 DRM pune, Central railwa
11. CTR (Primary) of 13.65 km in the section of KUN-KKDE. 25-7-05 17-3-06 DRM NEW DELHI, Northern railways
12. CTR (Secondary) From Km 11.2 between PRG-PBH-SLN sections. 5-1-06 12-5-06 DRM lucknow, Northern railways
13. A)9.10 Km CTR (P) Work by PQRS between Km 1193.00 to 1202.10 on DN Line of JHS-GWL section.

B) CTR (P) work by PQRS between HET-GHER section on GWL-AGC section.
08.08.2007 12.3.2008 DRM (W) Jhansi, N.C. Railways
14. 45 Km TSR by TRT in MTJ-AWR section. 04.01.2006 13.10.2008 DRM (W) Agra, N.C. Railways
15. Linking & Dismantling of BG Track Turnouts, Provision of SEJ, Glued Joints, Spreading of ballast, Leading of P.Way material and other misc. work from Km 1028.170 to 1013.355 between Anup Ganj-Chhandrauli section and Doubling between Utratla-Chhandrauli and Sultanpur-Bandhua Kalan section. 27.08.2007 24.4.2008 Dy. Chief Enguneer (C0nst), Kashmere Gate, Delhi, Northen Railways
16. CTR(S) of 10 km and TRR(S) of 2.5 km in loop line and Renewal of fan shaped turnout at various section on Delhi-Ambala section. 08.12.2006 26.5.2007 DRM New Delhi, Northern Railways
 