Ongoing Major Projects

Track Linking, Transportation and Welding
SL. No. Project Name Length in QTY Status of Project Project Cost (INR Mn)
1 Through Weld Renewal with Associated Track works at Kota Division, WC Rly, IR Track Linking 21875 Joints
80 % Work In Progress 157.60
2 IDH-BKI Section TWR By Using Mobile Flash Butt Welding Plant 17500 Joints From 81.00-148 In 52kg Rails at Agra Division, North Central Railway. Track Linking 12342 Joints
Work In Progress 83.50
3 Through Weld Renewal with Associated Track works at IDH - BXN Section, Agra Division, NC Rly, IR Track Linking 2000 Joints
Track Linking 47.96 Km
Work In Progress 21.30
4 BG Increasing Sleeper Density From M+4 To M+8 By PSC Sleeper in FKQ - SPGN Section, NF Rly, IR Track Linking 30 Km
Work In Progress 20.20
5 BG Increasing Sleeper Density From M+4 To M+8 By PSC 60Kg Sleeper in FKQ - SPGN Section, NF Rly, IR Track Linking 50 Km
Work In Progress 30.80
6 Complete Track Renewal in FKG-SPGN Section, Tinsukia Division, NF Rly, IR Track Linking 75.55 Km
Work In Progress 62.60
7 Loading/Unloading and Carriage of P.Way materials including fittings etc. from different location to site of work from Gauripur Yard to Abhayapur Yard Section of New Maynaguri – Jogighopa New B.G. Line Project of N.F.Rly, IR Track Linking 85 Km
Work In Progress 48.40
8 Spreading of 103500 m³ Depot Ballast Stacked In Station Yards of Murkongselek Gauge Conversion Project, NF Rly, IR. Track Linking 51.75 Km
Work In Progress 9.40
9 Commissioning, Testing, Installation of Railway Siding at Container Corporation of India Yard at Dadri, India Track Linking 1.77 Km
Work In Progress 56.40
10 Replacement of Various types of Turn Outs with Fan Shape Turn Outs at Firozpur Division, Northern Rly, IR Track Linking 134 Sets
Work In Progress 24.50
11 TWR by using mobile flash butt welds plant from 1299-1308, twr in 52kg rails at Jhansi division, North Central Railway. Track Linking 19900 Joints
Work In Progress 92.10
12 Nagda-Kota section through weld renewal in 60kg rails by using road cum stationary FBW ( Total 59.998) Track Linking 2760 Joints
Work In Progress 28.10
13 IDH-BKI Section- Through Weld Renewal 73.100 km from 5.90 to 52.500 & 54.500 to 81.00 in 52kg rails at site using road cum rail mobile / Stationary flash butt welding plant at Agra Division, North Central Railway. Flash Butt Welding 12600 Joints
Work In Progress 96.40
14 Through Weld Renewal in 60kg/52kg rails using Road-cum-rail mobile flash butt welding plant on Ruthiyai-Maksi section under DEN/West /Bhopal, West Central Railway Flash Butt Welding 12112 Joints
Work In Progress 91.17
15 Balance works of Earthwork, Bridgework, Track construction work and Track maintenance work of Railway Siding and MGR System of NTPC, Vindhyachal, Stage-IV (Package-2) Sleeper 2700 Nos
Supply of Ballast 6000 Cum
Flash Butt Welding 1756 Nos
100 % Work In Progress 41.60
And Many More…

Last Updates     Profile

Year End Turnover Net Profit Net Worth
March INR Mn US$ Mn INR Mn US$ Mn INR Mn US$ Mn
2018 788.05 11.19 97.99 1.39 495.50 7.04
2017 646.07 9.97 94.71 1.46 404.26 6.23
2016 561.05 8.16 82.21 1.20 309.55 4.50
2015 391.63 5.70 61.19 0.89 234.28 3.41
2014 319.67 4.65 22.50 0.33 173.09 2.52
2013 257.07 4.73 17.35 0.32 174.47 3.21
Read more..
Mechanical Track Laying of 670 Kms of Track between Dondo - Moatize of Sena Line & Inhamitnga – Marromeu Spur Line in Mozambique.

Transportation of PSC Sleepers in Pandharpur – Miraj - Latur project for Central Rly, IR

Complete Track Renewal work at Bhusawal for Central Rly, IR

Laying and Linking of BG Track in Pandharpur – Dhalgaon Section Central Rly, IR

Read more..
Through Weld Renewal with Associated Track works at Kota Division, WC Rly, IR

IDH-BKI Section TWR By Using Mobile Flash Butt Welding Plant 17500 Joints From 81.00-148 In 52kg Rails at Agra Division, North Central Railway.

Through Weld Renewal with Associated Track works at IDH - BXN Section, Agra Division, NC Rly, IR

BG Increasing Sleeper Density From M+4 To M+8 By PSC Sleeper in FKQ - SPGN Section, NF Rly, IR

Read more..

Railtech (RIPL) is one of the Oldest Rail Track Contractors with a Pan India & Global Presence.

ISO 9001-2008 Certified Company for Design and Execution of Railway Construction, Rehabilitation and Engineering Projects.