Ongoing Projects

LIST OF AWARDED WORKS UNDER PROCESS
Sl No. UID NO. Name & Place of work Railway Zone & Division LOA No & Date of award of contract Original cost of work / revised Cost Present Physical State of work in % Balance work yet to be completed in % Remark
KONKAN RAILWAY
1 531 TWR with Flash Butt Welding of 52 kg (90/72 UTS) rails/rail panels including USFD testing of welded joints conforming to IR Manual for Flash Butt Welding using Contractor's self propelled Rail‐cum‐road Mobile FBW Plants between km 378/1 to km 739/760 in the jurisdiction of Regional Engineer, Karwar, Konkan Railway Konkan Railway Corpn. Ltd. , Karwar KR/W/1/58/2019/06 dated 13.09.2019 21,50,98,798.14 66.18 33.82 Work in Progress
2 370 Casual Rail Renewal with New 52 kg/90 UTS rails (260m panels) and anti corrosive painting for rails under the jurisdiction of Senior Regional Engineer, Ratnagiri, Maharashtra State. (The rate shall be quoted excluding GST. GST will be payable extra as applicable). Konkan Railway Corpn. Ltd.,Ratnagiri KR/W/1/58/2019/22 dated 06.10.2020 6,47,24,626.00 - 100.00 Work not yet started
NORTH CENTRAL RAILWAY
3 466 Flash Butt Welding of 60 kg (HH/90 UTS) IRS T‐12‐96, 880 grade rails at CSP, Suberdarganj using contractor's own Flash Butt Welding Plant North Central Railway,Allahabad 219‐ W/Tender/FBW/TMS/20 17‐18/Pt‐I dated 07.11.2017 14,10,31,970.26 95.85 4.15 Work in Progress
A 581 Welding of free joints & replacement of old SKV joints by Mobile Flash Butt Welding technology for conversion into LWR and other associated works at various Loop Lines/Yards on Bina‐Sithouli section under Sr. DEN/Central/Jhansi's jurisdiction. North Central Railway,Jhansi JHANSI DIVISION‐ENGG / JHS‐ENGGC‐ 2020‐126 / 00826150031428 Dated: 28.01.2021 6,49,70,434.11 - 100.00 Work not yet started
4 525 Welding of Loop lines Rails at site using road cum rail mobile /Stationary Flash Butt Welding Plant in Allahabad ‐ Kanpur section under Sr. Divl. Engineer /II/North Central Railway /Allahabad North Central Railway,Allahabad 74‐W/9911/Bills dated 11.06.2019 3,40,17,594.41 13.17 86.83 Work in Progress
NORTH WESTERN RAILWAY
5 423 Flash butt welding of 60/52 kg New (72/90 UTS) Rail joint using MFBW plant in Connection with Rani ‐ Marwar Jn BG Patch doubling and thaiyat Hamira‐sanu new BG line project North Western Railway, Construction, Jaipur NWR/SC/Rani‐ Marwar/Civil‐309150802‐ R Dt. 17.09.2016 6,60,66,847.00 82.16 17.84 Work in Progress
6 427 FBW of 60 Kg New/Sh (72/90 UTS) Rail joint by using MFBW Plant in connection with Alwar‐Bandikui Doubling and Dausa‐Gangapurcity New Line Project North Western Railway, Construction, Jaipur NWR/SC/Alwar‐ Bandikui/Civil/51415080 3‐R dt. 16.11.2016 11,15,10,909.00 44.14 55.86 Work in Progress
7 437 Flash Butt Welding of 60 Kg/52 Kg New/SH Rails at Depot/Site using Mobile Flash Butt Welding Plant in Mavli ‐ Bari Sadri section in connection with Mavli ‐ Badi Sadri gauge conversion project. North Western Railway, Construction, Jaipur UDZMVJ‐ BI/GC/Welding/T‐3‐ R/474461437/Vol‐0 dt. 20.02.2017 3,93,26,610.00 - 100.00 Work in Progress
8 438 FBW of 60 kg / 52 kg New / SH rails at Depot/Site using MFBW plant in Dungapur ‐ Himmatnagar section in connection with udaipur ‐ Himmatnagar gauge conversa project North Western Railway, Construction, Jaipur NWR/SC/UDZ‐ HMT(GC)/Civil‐ 204140532 dt. 22.02.2017 5,31,70,254.00 49.26 50.74 Work in Progress
9 508 Flash Butt Welding (FBW) of 52Kg. / 60Kg. rails at depot / site using Mobile/ Stationary Flash Butt Welding Plant in connection with welding of rails in loop lines of various station over Jodhpur division. North Western Railway , Jodhpur Div. WB‐219‐W‐781/Line dated 29.11.2018 6,48,79,056.00 - 100.00 Work in Progress
10 510 Flash Butt Welding of 52 Kg/60 kg, New / SH Rails at depot / site using Mobile Flash Butt Welding plant in Jaipur‐ Ringus section in connection with Jaipur ‐ Sikar‐ Loharu & Sikar‐ Churuu GC Project. North Western Railway, Construction, Jaipur NWR/HQ/S&C/Single Tender/102140514 DT. 06.12.2018 17917200.00 29.01 70.99 Work in Progress
NORTHERN RAILWAY
11 430 Flash Butt Welding of 60kg/52kg (90/72 UTS) New/SH rails/rail panels including USFD testing of welded joints,using contractor's own mobile flash butt welding plant and USFD machine on loop/yard line locations of Northern Railway as per details in the tender document Northern Railway ,New delhi Baroda House S‐ 2/FBWP/TP/MUT/INSITU /15/1 dated 08.12.2016 11,19,13,238.00 79.44 20.56 Work in Progress
12 474 from single rail/Three rail panels to (60kg/52kg) LWR by Mobi Northern Railway,Moradabad Div. 74‐W/2/3/WA/Sr. DEN‐ C/133‐DRM‐MB‐17‐18 dt. 01.12.2017 10,38,10,274.00 72.47 27.53 Fore closure
13 991 Flash Butt Welding of Rail joints on Sirhind‐Amb Andore, Rajpura‐Bathinda‐Sriganga Nagar Section and Yard Lines on Saharanpur‐Ambala‐Ludhiana Section in the section of ADEN/Bathinda, Saharanpur, Sirhind & Rajpura under Sr.DEN‐IV/Ambala Northern Railway, Ambala 128‐W/280/15/Sr.DEN‐ IV/UMB/2018‐19 dated 20.08.2018 9,04,29,439.00 56.51 43.49 Work in Progress
14 500 TRR (P)= 41.77 Km. with loose rails & welding by Insitu Flash Butt Plant in the jurisdiction of Sr.DEN‐II/LKO 34.64 KM in JNH‐ZBD section and 7.13 km in DMW‐ON section) Northern Railway , Lucknow 48/WA/TEN/Work/ 10/Sr.DEN/‐II‐LKO/2018‐ 19 dated 09.10.2018 6,72,01,237.68 72.86 27.14 Work in Progress
15 548 TWR (Through Weld Renewal) 45.00 Km, by using Road cum Rail Mobile Flash Butt Welding plant of old AT Welds from SL Km 305.00 to 322.00 and 336 to 364 on BTI‐FZR section. Northern Railway, Ferozpu 124‐2019‐20‐DRM‐FZR / 00826150013581 dated 13.01.2020 8,18,24,349.62 - 100.00 Work in Progress
SOUTH EAST CENTRAL RAILWAY
16 447 Through Weld Renewal [TWR] by Mobile Flash Butt Welding Plant [MFBWP] in Raipur Division of South East Central Railway South East Central Railway,Raipur SECR/HQ/ENGG/Tr/MFB WP/420 25,23,99,781.71 28.83 71.17 Work in Progress
17 448 Through Weld Renewal [TWR] by Mobile Flash Butt Welding Plant [MFBWP] in Nagpur Division of South East Central Railway South East Central Railway,Nagpur SECR/HQ/ENGG/Tr/MFB WP/420 22,95,67,511.26 20.42 79.58 Work in Progress
18 485 TWR (TWR) by mobile Flash Butt Welding Plant (MFBWP) for 6.604 km between Jharsuguda‐Champa‐Gevra Road section and 13.94 km between Anuppur‐Ambikapur section of Bilaspur division South East Central Railway, Bilaspur DRM‐ENGG‐BSP‐T‐117‐ 17‐18/TWR/BSP/576 dated 28.06.2018 3,08,39,509.00 56.36 43.64 Termination notice issued under force majure clause
19 504 Through Weld Renewal (TWR) by Mobile Flash Butt welding Plant (MFBWP) for 29.00 Km between between Anuppur‐ Ambikapur section under the jurisdiction of Assistant Divisional Engineer/Manendragarh. South East Central Railway, Bilaspur DRM‐ENGG‐BSP‐T‐78‐18‐ 19/TWR/MDGR/307 dated 06.12.2018 4,52,19,351.00 72.79 27.21 Termination notice issued under force majure clause
20 547 Through Weld Renewal By Mobile Flush Butt Welding for 74.44 km in Gondia‐Chandafort (BG) Section under the jurisdiction of Sr.ADEN/Nagbhir. South East Central Railway Nagpur S‐22‐NGP‐2019‐20 / 00826150013143 dated 07.01.2020 13,01,44,291.73 40.03 59.97 Work in Progress
21 559 TRR (S) 25.80 Km of existing 52 Kg, 70 UTS rail with 60Kg, 90 UTS SH rail in Tumsar ‐ Tirodi branch line with Flash butt welding under the jurisdiction of Sr.DEN/Central/Nagpur. South East Central Railway Nagpur C‐41‐NGP‐2019‐2020 / 00826150017835 dated 23.03.2020 6,05,64,373.03 45.51 54.49 Work in Progress
SOUTH WESTERN RAILWAY
22 561 SW‐I: Bangalore ‐Hassan Through weld renewal for a length of 39 kms from 124/300‐ 163/300. SW‐II: Bangalore‐ Salem Through weld renewal for a length of 23 kms from Km 23/000‐36/000 and 55/000‐65/000. SW‐II: SBC‐ SA section: Through weld renewal for a length of 23 kms from km 23/000‐36/000 and 55/000‐ 65/000 in ADEN/DPJ section. Maintenance period 3 months South Western Railway,Bangalore 02SBC20of24‐2‐ 20item04 / 00826150020398 dated 15.06.2020 11,67,58,213.20 8.39 91.61 Work in Progress
23 565 Hosapete‐ Ballari Section:‐ Through Weld Renewal between Hosapete to Ballari from Km 161/0‐212/0 (UP) Total length of 51 km. South Western Railway,Hubli H/W.148/I/E/31/2019/0 1/W5 dated 13.07.2020 12,02,35,962.46 21.09 78.91 Work in Progress
SOUTHERN RAILWAY
24 569 Thanjavur‐Nagore‐Karaikal Section: Through Weld Renewal using Mobile Flash Butt welding plant under line black at KM 30.500 ‐ 36.500 and KM 40.000 ‐ 53.500 for a total length of 19.50Km between Nidamangalam and Thiruvarur stations in Senior section Engineer/P.Way/A‐Thiruvarur section. Southern Railway , TRICHCHIRAPPALLI TPJ‐03‐2020‐ 20 / 00826150025867 dated 18.09.2020 5,51,62,070.21 - 100.00 Work not yet started
WEST CENTRAL RAILWAY
25 568 Strengthening of Main line by replacement of old and defective Welds by 60 Kg/ 52Kg Rails Using Road‐Cum‐Rail‐Mobile Flash Butt Welding Plant between kms. 587.0 kms to 597.0 kms ( 14 Kms b/w 587 ‐ 597) UP & DN line under ADEN/HD section West Central Railway,Bhopal WCR‐BPL‐W‐2020‐21‐ S‐05‐39 / 00826150025570 dated 12.09.2020 2,45,23,110.91 - 100.00 2,45,23,110.91
26 573 Through weld renewal in 60 Kg‐52 Kg Rails using Road ‐Cum‐ Rail Mobile Flash Butt Welding Plant and or Stationary Flash Butt Welding Plant ‐ 13249 Joints (Itarsi ‐ Jabalpur ‐ 4955 Joints, Jabalpur ‐ Katni ‐ 4445 Joints and Bina ‐ Katni ‐ 3849 Joints) on Jabalpur Division West Central Railway,Jabalpur DRMW‐JBP‐103‐2020 / 00826150027201 dated 17.10.2020 16,02,24,552.41 - 100.00 Work not yet started
WESTERN RAILWAY
27 512 Ratlam Division :‐ Flash Butt Welding of 52 Kg/60Kg rails by using Contractor own Mobile Flash Butt Welding Plant on Godhra ‐ Nagda and Chanderiya ‐ Ratlam ‐ Dr Ambedkar Nagar Section in connection with various sanctioned track works in jurisdiction of Senior DEN(North) and DEN (West) of Ratlam Division of Western Railway Western Railway,Ratlam Div. Ratlam/2018‐19/154 dt.07.01.2019 12,89,64,216.69 94.19 5.81 Work in Progress
28 519 Virar ‐ Surat‐ section. Flash Butt Welding of 90R/52kg/60kg rails by using contractors own Mobile Flash Butt Welding Plant in connection with sanctioned track work (i) CTR(S) = 1.71km in Dahanu Road Yard, Valsad Yard, Udhna Yard (ii) Replacement of free joint in Udhna Yard. Western Railway,Mumbai W 632/4341 ,4342,4340,4334/W A/ 18‐19 dated 05.03.2019 8,92,66,710.73 57.10 42.90 Work in Progress
29 535 Welding of free joints, TWR and strengthening of loop lines and converting of loop lines into LWR by mobile flash butt weld on Palanpur‐ Gandhidham section‐ 6100 Nos Western Railway,Ahmedabad DRM‐ADI‐ 316‐2018‐19 / 00826150007546 Dated: 04/10/2019 7,28,94,946.29 49.76 50.24 Work in Progress
30 552 Vadodara Division:‐Flash Butt Welding of 90R/52 Kg/60Kg rails by using Contractors own Mobile Flash Butt Welding Plant in connection with sanctioned elimination of AT welds having carried GMT more than 50% , defective welds on main lines in various station yards and converting passenger running loop lines/other important lines in to LWR in various station yards over Vadodara Division.(Re‐invited)(R‐ 5) Western Railway,Vadodara DRM‐BRC‐117‐of‐2019‐ 20 / 00826150014594 dated 28.01.2020 12,68,68,006.00 - 100.00 Work not yet started
31 560 Flash Butt Welding of 52 Kg/ 60 Kg rails by using contractor's own Mobile Flash Butt Welding plant under Divisional Engineer (West) Rajkot's jurisdiction Western Railway,Rajkot ENGG/DRM‐RJT‐19‐E‐ 89/008266150018549 dated. 30.04.2020 3,58,42,674.70 90.18 9.82 Work in Progress
32 572 CCG ‐ VR section:‐Flash Butt Welding of 90R/52 Kg/60Kg rails by using Contractor's own Mobile Flash Butt Welding Plant in connection with various sanctioned works of Track Renewal over Mumbai Division. Western Railway,Mumbai BCT‐20‐21‐57 / 00826150027017 dated 14.10.2020 15,17,39,763.93 - 100.00 Work not yet started
33 574 Palanpur‐ Mahesana:‐ Complete track renewal of existing 52 Kg track with 60 Kg track by PQRS (Total = 19.241 Km), Deep screening by BCM and associate works in the jurisdiction of Divisional Engineer (North) Ahmedabad. Western Railway , Ahmedabad DRM‐ADI‐ 155‐2020‐21 / 00826150029213 dated 07.12.2020 5,86,41,297.12 - 100.00 Work not yet started
34 575 Palanpur‐ Mahesana:‐ Complete track renewal of existing 52 Kg track with 60 Kg track by PQRS (Total = 36.744 Km), Deep Screening by BCM and Laying and linking of BG track for PQRS siding in connection with CTR work and associate works in the jurisdiction of Divisional Engineer (North)Ahmedabad. Western Railway , Ahmedabad DRM‐ADI‐ 156‐2020‐21 / 00826150029214 dated 07.12.2020 9,19,95,981.97 - 100.00 Work not yet started
Total 3,30,97,45,161.57

© Copyright 2021 Railtech Infraventure Private Limited